ENTERPRISE, Ala. (WDHN) — Roadwork in Enterprise that was previously delayed is now set to start on Monday, June 20th.

Phase 1 of the project is the resurfacing of Plaza Drive from the intersection at East Park south to Boll Weevil Circle at Highway 167 South, according to the Alabama Department of Transportation.

The work on Plaza Drive is expected to begin Monday. The work will be done during the daytime hours and should take about a week, ALDOT officials said.

Phase 2 will be resurfacing East Park from the BWC/Highway 84 East intersection to South Main Street near Enterprise City Hall.

On Monday, June 27, ALDOT is scheduled to start work on Main Street at City Hall and work north to the intersection of the Boll Weevil Circle and Highway 84 West.

The road will be worked on between 6 p.m. and 6 a.m. Sunday through Thursday nights. It is expected to take about two weeks to complete.